Issue details

School Organisation Planning: Moorland Primary School approval of funding

Under delegated authority, the Director of Education, gave authorisation to proceed to tender on 12 November 2021. 

           To replace the Moorland Early years unit

           provide a replacement Flying start from Willows high school

           A crèche and community room for parenting and community use

           A 20place Specialist Resource base for Complex Leaning needs.

           Demolition of derelict caretakers house.

 

 

It its meeting on 14 July 2022, Cabinet agreed to a 20 place Specialist Resource Base for primary aged children with Complex Learning Needs at Moorland Primary School from September 2023.

 

The quotations now stand above the delegated authority approvals by the Director of Education.

 

The purpose of the report is to seek Cabinet approval to proceed with the contractor quotation to progress the project and avoid further delay.

 

Decision type: Key

Decision status: Recommendations Approved

Notice of proposed decision first published: 11/11/2022

Decision due: 15 Dec 2022 by Cabinet

Scrutiny Consideration: Amber

Decisions

Agenda items