Decision details

South East & Mid Wales Highways and Civil Engineering Framework 4.

Decision Maker: Corporate Director Resources & Section 151 Officer

Decision status: For Determination

Is Key decision?: Yes

Is subject to call in?: Yes

Decision:

Appendix A to the report is not for publication as it contains exempt information of the description in paragraph 14 part 4 of Schedule 12A of the Local Government Act 1972 and in all the circumstances of the case, the public interest in maintaining the exemption outweighs the public interest in disclosing the information (paragraph 21 of part 5 of Schedule 12A of the Local Government Act 1972).

 

AGREED: that

 

1.   those organisations identified in Appendix A as being shortlisted and eligible to be taken forward to the next stage of the procurement process be invited to tender.

 

2.   the invitation to tender documentation, including the evaluation criteria, draft framework agreement and schedules be approved and issued to those organisations identified in Appendix A.

 

           

Reasons for the decision:

To continue the process to enable appoint contractors to the South East Wales Highways and Civil Engineering Framework, hosted by Cardiff Council, to maintain a compliant procurement route for Highways and Civils projects third party spend, for a period of four (4) years from January 2023 – December 2026.

 

Publication date: 01/06/2022

Date of decision: 27/05/2022

Effective from: 15/06/2022