Decision Maker: Director of Education and Lifelong Learning
Decision status: Recommendations Approved
Is Key decision?: Yes
Is subject to call in?: Yes
Agreed: that
· the proposed procurement route be authorised and tenders invited via the SEWSCAP 3 Lot 11 Framework Agreement in order to procure contractors to construct the additional accommodation and facilities as set out in the report.
· the evaluation criteria set out in the report be approved
To enable the projects to progress and meet the required completion date
Publication date: 03/02/2022
Date of decision: 08/12/2021
Effective from: 15/02/2022