The Welsh Government is constructing Phase 1 of the Eastern Bay Link between Butetown Tunnels and Ocean Way Roundabout at a cost of £57m at no cost to Cardiff Council. The Welsh Government has invited Council Officers to meet with the M4 Project Team to better understand the scope and potential impacts of the M4 project.
The report seeks to delegate authority to the Director to engage with Welsh Government to progress a joint study of options for the next phases of the Eastern Bay Link.
Math o fusnes: Key
Statws: Argymhellion Cymeradwy
Hysbysiad o benderfyniad arfaethedig wedi’i gyhoeddi gyntaf: 16/12/2016
Angen Penderfyniad: 15 Rhag 2016 Yn ôl Cabinet
Prif Aelod: Aelod y Cabinet dros Drafnidiaeth, Cynllunio a Chynaliadwyedd
Prif Gyfarwyddwr: Director of City Operations
Scrutiny Consideration: GREEN