Lamby Way Solar Farm

Decision:

The Appendices of this report are exempt from publication because they contain information of the kind described in paragraphs 14 and 21 of parts 4 and 5 of Schedule 12A of the Local Government Act 1972

 

 

RESOLVED: that the Business Case and Invest to Save allocation for the scheme be approved and the delivery plan for implementation be commenced

 

Minutes:

The Appendices of this report are exempt from publication because they contain information of the kind described in paragraphs 14 and 21 of parts 4 and 5 of Schedule 12A of the Local Government Act 1972

 

Cabinet received the detailed business case for a solar farm at Lamby Way, based in a capacity of 7.5mw. It was reported that an outline deal had been reached with an organisation to take 4.5mw of the capacity at the Solar Farm over a twenty year period and this assisted the viability of the project. It was proposed that the project progress to the next phase which would include the submission of a planning application and the commencement of a procurement process for a design and build contractor, and operation and maintenance contractor for the scheme. The final costings for the scheme, based on the outcome of the formal procurement process would be brought to Cabinet for final approval.

 

RESOLVED: that the Business Case and Invest to Save allocation for the scheme be approved and the delivery plan for implementation be commenced

 