ISV Velodrome Construction

Decision Maker: Director of Economic Development

Decision status: For Determination

Is Key decision?: Yes

Is subject to call in?: Yes

Decision:

Agreed: that agreement be given to authorise the award of stage 1 of the contract to Andrew Scott Ltd as the preferred contractor, following the compliant tender process, to progress the initial design and review the costs to construct the velodrome and its associated Performance Hub building and note the provisions relating to stage 2 as set out in the report.

Reasons for the decision:

To enable the contractor to provide advice, information and support that will enable the project to complete the design works and confirm the costs of the Velodrome and Performance Hub.  These costs will then be presented back for Cabinet consideration (as part of the final business case) before stage 2 of the contract can be proceeded with.

 

 

 

Publication date: 26/10/2021

Date of decision: 21/10/2021