Decision Maker: Director of Planning, Transport & Environment
Decision status: Recommendations Approved
Is Key decision?: Yes
Is subject to call in?: Yes
Agreed: that
1. a procurement be commenced for design and construction of a “Private Wire” connection between the Lamby Way solar farm and a nearby energy customer.
2. the evaluation criteria set out in the report be approved
The reason for the recommended decision is: to facilitate the completion of the Lamby Way Solar Farm Project
Publication date: 26/11/2020
Date of decision: 16/11/2020
Effective from: 27/11/2020