Decision details

Millennium Walkway Deck Replacement

Decision Maker: Director of Planning, Transport & Environment

Decision status: Recommendations Approved

Is Key decision?: Yes

Is subject to call in?: Yes

Decision:

Agreed: that

 

1.       Tenders be invited from suppliers within the South East & Mid Wales Highways Framework for the replacement of the timber decking and structural members.  The estimated value is £1.7m.

 

2.       The proposed tender evaluation criteria of 70% cost 30% Quality be agreed

 

Reasons for the decision:

To enable the Council to appoint a contractor to carry out the replacement of the timber decking and structural members

 

 

 

Publication date: 15/09/2020

Date of decision: 08/09/2020

Effeithiol O: 25/09/2020