Senghennydd Road Proposed Cycle Superhighway - Arrangements for the Procurement of Principal Contractor
Decision Maker: Director of Planning, Transport & Environment
Decision status: Recommendations Approved
Is Key decision?: Yes
Is subject to call in?: Yes
Decision:
Agreed: that, subject to there being no successful application as set out in paragraph 15 of the report, Alun Griffiths (Contractors) Ltd.be appointed as principal contractor to carry out the construction of the Cycle Superhighway at Senghennydd Road under the South East Wales Framework Lot 9. The value of contract is £1,192,112.10 and the anticipated start date is 18th March 2019.
Reasons for the decision:
A mini-competition was undertaken through the South East Wales Framework and Alun Griffiths (Contractors) Ltd. achieved the highest percentage score in the tender evaluation.
Publication date: 13/02/2019
Date of decision: 08/02/2019
Effective from: 23/02/2019