Decision details

Framework For Roof Upgrades To Houses

Decision Maker: Corporate Director of People and Communities

Decision status: Recommendations Approved

Is Key decision?: Yes

Is subject to call in?: Yes

Decision:

AGREED: that

 

1.      the proposed overarching evaluation criteria as detailed in the body of this report be approved.

 

2.      the commencement of the procurement and the issue of the OJEU contract notice and PQQ documentation be authorised.

 

Reasons for the decision:

To commence the process to enable the Council to appoint two contractors to a framework to deliver roof upgrades for a period of 2 years from April 2019, with the option to extend for up to a further 2 years.

 

 

 

 

Publication date: 13/09/2018

Date of decision: 12/09/2018

Effective from: 25/09/2018