New High School In The West Project - Change Psc Contract For Detailed Design To A Later Design Stage

Decision Maker: Director of Education and Lifelong Learning

Decision status: Recommendations Approved

Is Key decision?: Yes

Is subject to call in?: Yes

Decision:

AGREED: that Riba Stage 4 for the detailed design of the Cardiff West Community High School be incorporated into the services contract (PSC).

 

 

Reasons for the decision:

To enable the project to progress with a higher degree of cost certainty, we would like to and proceed to detailed design, and meet the required completion date. Taking the school to this later design stage ahead of full planning application; thus reducing the risk for both parties and ensuring greater value for the money for the Council.

 

Publication date: 29/03/2017

Date of decision: 22/03/2017

Effeithiol O: 08/04/2017