Decision details

SEWSCAP3 Collaborative Schools and Public Buildings Construction Framework Award

Decision Maker: Corporate Director Resources & Section 151 Officer

Decision status: Recommendations Approved

Is Key decision?: Yes

Is subject to call in?: Yes

Decision:

Agreed: that the award of the successful contractors on to the SEWSCAP(3) Collaborative Construction Framework be approved.

Reasons for the decision:

An OJEU compliant procurement has been undertaken following the RESTRICTED procedure, shortlisting contractors from pre-qualification through to invitation to tender (ITT.) The following list (see Appendix A) are the successful contractors who have achieved a place against the respective geographic lots. The council is minded to utilise the SEWSCAP3 framework in respect of its 21st Century Band B capital commitments.

 

Publication date: 30/05/2019

Date of decision: 28/05/2019

Effective from: 11/06/2019