Decision Maker: Corporate Director of People and Communities
Decision status: Recommendations Approved
Is Key decision?: Yes
Is subject to call in?: Yes
Agreed: that
1. the outcome of the evaluation process as set out in Appendix A be noted in terms of the bidders ranking;
2. officers be instructed to inform those parties that tendered in this matter (as well as those who expressed an interest in this matter) of the outcome of the evaluation process and proposed way forward (as detailed in the report);
3. the Framework Agreement be formally concluded with those organisations highlighted yellow in Appendix A to the report
To appoint two contractors to a framework to roof upgrades to houses for a period of 2 years from May 2019 with the option to extend for up to a further 2 years.
Publication date: 18/04/2019
Date of decision: 09/04/2019
Effeithiol O: 02/05/2019